Tabla de Datos Para Ms Project

20
PARTIDA DESCRIPCION METRADO (1) RECURSO TIPO TRABAJO MO+EQ 1.01 1.00 TOTAL 1.02 1.00 TOPOGRAFO(S) AYUDANTE(S) DE TOPOGRAFIA NIVEL TOPOGRAFICO JALON TOPOGRAFICO MIRA TOPOGRAFICA TEODOLITO TOPOGRAFICO TOTAL 1.03 1.00 TOTAL 2.01 106,006.27 OFICIAL PEON MARTILLO NEUMATICO DE 29 kg TOTAL 2.02 39,589.31 PEON TOTAL 2.03 84,421.06 OFICIAL CAMION VOLQUETE DE 15 m3 TOTAL MOVILIZACION Y DESMOVILIZACION TRAZO Y REPLANTEO INSTALACIONES PROVISIONALES DEMOLICIONES VARIAS COMPRESORA NEUMATICA 250 - 330 PCM - 87 HP CARGADOR S/LLANTA 125 HP, 2.50 yd3 CORTE EN MATERIAL SUELTO PARA PAVIMENTOS EXCAVADORA SOBRE ORUGAS 115- 165 HP ELIMINACION DE EXCEDENTE D=20 km CARGADOR SOBRE LLANTAS DE 125-135 HP 3 yd3

description

para ingresar datos a project

Transcript of Tabla de Datos Para Ms Project

Page 1: Tabla de Datos Para Ms Project

TRABAJO PRESUPUESTADO

PARTIDA DESCRIPCION METRADO (1) RECURSO TIPO TRABAJO MO+EQ UND

1.01 1.00

TOTAL (4)

1.02 1.00

TOPOGRAFO(S) díaAYUDANTE(S) DE TOPOGRAFIA díaNIVEL TOPOGRAFICO díaJALON TOPOGRAFICO díaMIRA TOPOGRAFICA díaTEODOLITO TOPOGRAFICO día

TOTAL (4)

1.03 1.00

TOTAL (4)

2.01 106,006.27

OFICIAL hh 1.00

PEON hh 3.00

MARTILLO NEUMATICO DE 29 kg hm 2.00

hm 1.00

hm 1.00

TOTAL (4)

2.02 39,589.31

PEON hh 3.00

hm 1.00

TOTAL (4)

2.03 84,421.06

OFICIAL hh 1.00

hh 1.00

CAMION VOLQUETE DE 15 m3 hm 5.00TOTAL (4)

CUADRILLA (2)

MOVILIZACION Y DESMOVILIZACION

TRAZO Y REPLANTEO

INSTALACIONES PROVISIONALES

DEMOLICIONES VARIAS COMPRESORA NEUMATICA 250 -

330 PCM - 87 HP

CARGADOR S/LLANTA 125 HP, 2.50 yd3

CORTE EN MATERIAL SUELTO PARA PAVIMENTOS

EXCAVADORA SOBRE ORUGAS 115-165 HP

ELIMINACION DE EXCEDENTE D=20 km

CARGADOR SOBRE LLANTAS DE 125-135 HP 3 yd3

Page 2: Tabla de Datos Para Ms Project

3.01 98,024.03

OFICIAL hh 1.00

PEON hh 5.00

MARTILLO NEUMATICO DE 29 kg hm 1.00

hm 1.00

hm 0.50

TOTAL (4)

3.02 98,024.03

OFICIAL hh 1.00

PEON hh 5.00

hm 1.00

MOTONIVELADORA 125 HP hm 1.00

CAMION CISTERNA 2,000 Gl AGUA hm 0.50

TOTAL (4)

3.03 98,024.03

OFICIAL hh 1.00

PEON hh 5.00

hm 1.00

MOTONIVELADORA 125 HP hm 1.00

CAMION CISTERNA 2,000 Gl AGUA hm 0.50

TOTAL (4)

3.04 98,024.03

OFICIAL hh 1.00

PEON hh 3.00

TRACTOR DE TIRO DE 63 HP hm 1.00

hm 1.00

hm 1.00

TOTAL (4)

3.05 98,024.03

OPERARIO hh 1.00

OFICIAL hh 3.00

PEON hh 10.00

CONFORMACION DE SUBRASANTE COMPRESORA NEUMATICA 250 -

330 PCM - 87 HP

CARGADOR S/LLANTA 125 HP, 2.50 yd3

SUB-BASE GRANULAR E=0.20 m

RODILLO LISO VIBRATORIO AUTOPROPULSADO 7- 9 ton

BASE GRANULAR e=0.20 m

RODILLO LISO VIBRATORIO AUTOPROPULSADO 7- 9 ton

IMPRIMACION ASFALTICA CAMION IMPRIMADOR 6X2 178-

210 HP 1,800 gl

BARREDORA MECANICA 10-20 HP 7 P.LONG.

CARPETA ASFALTICA EN CALIENTE E=4cm

Page 3: Tabla de Datos Para Ms Project

3.05 98,024.03 TRACTOR DE TIRO DE 63 HP hm 1.00

hm 1.00

hm 1.00

TOTAL (4)

4.01 4,600.97PEON hh 10.00

TOTAL (4)

4.02 5,172.30

OFICIAL hh 1.00

hm 1.00

CAMION VOLQUETE DE 15 m3 hm 5.00TOTAL (4)

4.03 26,524.57

OFICIAL hh 1.00

PEON hh 5.00

hm 1.00

MOTONIVELADORA 125 HP hm 1.00

CAMION CISTERNA 2,000 Gl AGUA hm 0.50

TOTAL (4)

4.04 26,524.57

OFICIAL hh 1.00

PEON hh 6.00

hm 1.00

MOTONIVELADORA 125 HP hm 1.00

CAMION CISTERNA 2,000 Gl AGUA hm 0.20

TOTAL (4)

4.05 26,524.57

OPERARIO hh 4.00

OFICIAL hh 2.00

PEON hh 4.00

TOTAL (4)

5.01 4,474.12

OPERARIO hh 2.00

CARPETA ASFALTICA EN CALIENTE E=4cm CAMION IMPRIMADOR 6X2 178-

210 HP 1,800 gl

BARREDORA MECANICA 10-20 HP 7 P.LONG.

EXCAVACION EN MATERIAL SUELTO PARA VEREDAS Y SARDINELES

ELIMINACION DE EXCEDENTE D=20 km

CARGADOR SOBRE LLANTAS DE 125-135 HP 3 yd3

CONFORMACION DE SUBRASANTE

RODILLO LISO VIBRATORIO AUTOPROPULSADO 7- 9 ton

BASE PARA VEREDAS e=0.10m

RODILLO LISO VIBRATORIO AUTOPROPULSADO 7- 9 ton

VEREDA DE CONCRETO f'c=210 kg/cm2, e=4"

PINTURA ZONAL, DE SIMBOLOS Y LETRAS

Page 4: Tabla de Datos Para Ms Project

5.01 4,474.12 PEON hh 2.00

TOTAL (4)

5.02 49.76TOTAL (4)

5.03 60.00

TOTAL (4)

JORNAL 8.00 HORAS

LOS PRESUPUESTOS CONDICIONAN A UNA CANTIDAD FIJA DE TRABAJO ASIGNADA A CADA PARTIDA PARA SU EJECUCION

PINTURA ZONAL, DE SIMBOLOS Y LETRAS

PANELES IMFORMATIVOS

SEÑAL OCTOG. PREVENTIVA 75cmx75cm

TIPO TRABAJO FIJO: LA COLUMNA (4) ES LA CANTIDAD TOTAL DE RECURSO PRODUCTO DE LOS DATOS METRADO (PRESUPUESTO) E INSUMO (ANALISIS DE PRECIOS UNITARIOS) Y CONSTITUYE UN DATO FIJO

Page 5: Tabla de Datos Para Ms Project

TRABAJO PRESUPUESTADO

INSUMO (3) PU (5) TOTAL (6)=(4)X(5) UND

0.00 0.00 0.00 vje

0.00 0.00 0.00 vje

TOTAL (4) 0.00 0.00180.0000 180.00 69.60 12,528.00360.0000 360.00 62.40 22,464.00

90.0000 90.00 45.00 4,050.0090.0000 90.00 6.50 585.00

360.0000 360.00 8.50 3,060.0090.0000 90.00 70.00 6,300.00

TOTAL (4) 1,170.00 48,987.00

0.00 0.00 0.00 vje

TOTAL (4) 0.00 0.00

0.0533 5,650.13 10.15 57,348.86 %mo

0.1600 16,961.00 9.10 154,345.13

0.1067 11,310.87 21.50 243,183.68

0.0533 5,650.13 50.50 285,331.78

0.0533 5,650.13 150.00 847,520.13

TOTAL (4) 45,222.27 1,587,729.58

0.0429 1,698.38 9.10 15,455.27 %mo

0.0143 566.13 270.00 152,854.33

TOTAL (4) 2,264.51 168,309.600.0200 1,688.42 10.15 17,137.48

0.0200 1,688.42 150.00 253,263.18

0.1000 8,442.11 130.00 1,097,473.78TOTAL (4) 11,818.95 1,367,874.44

CANTIDAD TOTAL (4)=(1)X(3)

RECURSO TIPO MATERIAL Y COSTO

FLETE TERRESTRE EN PLATAFORMA (IDA)

FLETE TERRESTRE EN PLATAFORMA (VUELTA)

SERVICIO DE ALQUILER DE CONTEINER

HERRAMIENTAS MANUALES

HERRAMIENTAS MANUALES

Page 6: Tabla de Datos Para Ms Project

0.0067 656.76 10.15 6,666.12 %mo

0.0333 3,264.20 9.10 29,704.22

0.0067 656.76 115.50 75,855.90

0.0067 656.76 145.00 95,230.35

0.0033 323.48 110.00 35,582.72

TOTAL (4) 5,557.96 243,039.31

0.0100 980.24 10.15 9,949.44 %mo

0.0500 4,901.20 9.10 44,600.93 m3

0.0100 980.24 115.50 113,217.75

0.0100 980.24 145.00 142,134.84

0.0050 490.12 110.00 53,913.22

TOTAL (4) 8,332.04 363,816.19

0.0100 980.24 10.15 9,949.44 %mo

0.0500 4,901.20 9.10 44,600.93 m3

0.0100 980.24 115.50 113,217.75

0.0100 980.24 145.00 142,134.84

0.0050 490.12 110.00 53,913.22

TOTAL (4) 8,332.04 363,816.19

0.0016 156.84 10.15 1,591.91 %mo

0.0048 470.52 9.10 4,281.69 KEROSENE INDUSTRIAL gal

0.0016 156.84 54.00 8,469.28 ASFALTO RC-250 gal

0.0016 156.84 126.00 19,761.64

0.0016 156.84 57.50 9,018.21

TOTAL (4) 1,097.87 43,122.73

0.0040 392.10 11.25 4,411.08 %mo

0.0120 1,176.29 10.15 11,939.33 MEZCLA ASFALTICA m3

0.0400 3,920.96 9.10 35,680.75 m3

HERRAMIENTAS MANUALES

HERRAMIENTAS MANUALES

MATERIAL GRANULAR PARA SUB-BASE

HERRAMIENTAS MANUALES

MATERIAL GRANULAR PARA BASE

HERRAMIENTAS MANUALES

HERRAMIENTAS MANUALES

TRANSPORTE DE MEZCLA ASFALTICA

Page 7: Tabla de Datos Para Ms Project

0.0040 392.10 125.00 49,012.02

0.0040 392.10 125.00 49,012.02

0.0040 392.10 130.00 50,972.50

TOTAL (4) 6,665.63 201,027.68

2.6667 12,269.41 9.10 111,651.60 %mo

TOTAL (4) 12,269.41 111,651.600.0200 103.45 10.15 1,049.98

0.0200 103.45 150.00 15,516.90

0.1000 517.23 130.00 67,239.90TOTAL (4) 724.12 83,806.78

0.0067 177.71 10.15 1,803.80 %mo

0.0333 883.27 9.10 8,037.74

0.0067 177.71 115.50 20,526.04

0.0067 177.71 145.00 25,768.62

0.0033 87.53 110.00 9,628.42

TOTAL (4) 1,503.94 65,764.62

0.0320 848.79 10.15 8,615.18 %mo

0.1920 5,092.72 9.10 46,343.73 m3

0.0320 848.79 30.00 25,463.59

0.0320 848.79 43.50 36,922.20

0.0064 169.76 110.00 18,673.30

TOTAL (4) 7,808.83 136,017.99

0.3200 8,487.86 11.25 95,488.45 %mo

0.1600 4,243.93 10.15 43,075.90 kg

0.3200 8,487.86 9.10 77,239.55 m3

ADITIVO CURADOR galMADERA TORNILLO p2

TOTAL (4) 21,219.66 215,803.90

0.4571 2,045.12 11.25 23,007.60 %mo

HERRAMIENTAS MANUALES

HERRAMIENTAS MANUALES

HERRAMIENTAS MANUALES

MATERIAL GRANULAR PARA BASE

HERRAMIENTAS MANUALES

CLAVOS PARA MADERA CON CABEZA

CONCRETO PREMEZCLADO F'C=210 kg/cm2

HERRAMIENTAS MANUALES

Page 8: Tabla de Datos Para Ms Project

0.4571 2,045.12 9.10 18,610.59 PINTURA DE TRANSITO gal

0.00 DISOLVENTE XILOL galTOTAL (4) 4,090.24 41,618.20

0.00 0.00 m2

TOTAL (4) 0.00 0.00

0.00 0.00 und

TOTAL (4) 0.00 0.00

LOS PRESUPUESTOS CONDICIONAN A UNA CANTIDAD FIJA DE TRABAJO ASIGNADA A CADA PARTIDA PARA SU EJECUCION

SERVICIO FAB. E INST. SEÑAL INFORMATIVA

SERVICIO FAB. E INST. SEÑAL OCTOG. PREVENTIVA

: LA COLUMNA (4) ES LA CANTIDAD TOTAL DE RECURSO PRODUCTO DE LOS DATOS METRADO (PRESUPUESTO) E INSUMO (ANALISIS DE PRECIOS UNITARIOS) Y CONSTITUYE UN DATO FIJO

Page 9: Tabla de Datos Para Ms Project

TRABAJO PRESUPUESTADO TRABAJO PLANIFICADO

INSUMO (3) PU (5) TOTAL (6)=(4)X(5)

6.0000 6.00 1,800.00 10,800.00 0.00

6.0000 6.00 1,800.00 10,800.00 0.00

12.00 21,600.00 TOTAL (10)1.00 0.001.00 0.001.00 0.001.00 0.001.00 0.001.00 0.00

TOTAL (10)

24.0000 24.00 1,350.00 32,400.00 0.00

24.00 32,400.00 TOTAL (10)

0.0500 5,300.31 2.00 10,600.63 6.00 6.00

6.00 18.00

6.00 12.00

6.00 6.00

6.00 6.00

5,300.31 10,600.63 TOTAL (10)

0.0500 1,979.47 0.39 771.99 2.00 6.00

2.00 2.00

1,979.47 771.99 TOTAL (10)3.00 3.00

3.00 3.00

3.00 15.000.00 0.00 TOTAL (10)

CANTIDAD TOTAL (4)=(1)X(3)

N° CUADRILLAS (7)

TOTAL RECURSO (8)=(7)X(2)

Page 10: Tabla de Datos Para Ms Project

0.0500 4,901.20 0.37 1,813.44 3.00 3.00

3.00 15.00

3.00 3.00

3.00 3.00

3.00 1.50

4,901.20 1,813.44 TOTAL (10)

0.0500 4,901.20 0.56 2,744.67 3.00 3.00

0.2500 24,506.01 38.00 931,228.29 3.00 15.00

3.00 3.00

3.00 3.00

3.00 1.50

29,407.21 933,972.96 TOTAL (10)

0.0500 4,901.20 0.56 2,744.67 3.00 3.00

0.2500 24,506.01 42.00 1,029,252.32 3.00 15.00

3.00 3.00

3.00 3.00

3.00 1.50

29,407.21 1,031,996.99 TOTAL (10)

0.0500 4,901.20 0.06 294.07 1.00 1.00

0.0650 6,371.56 6.50 41,415.15 1.00 3.00

0.2600 25,486.25 5.00 127,431.24 1.00 1.00

1.00 1.00

1.00 1.00

36,759.01 169,140.46 TOTAL (10)

0.0500 4,901.20 0.53 2,597.64 2.00 2.00

0.0500 4,901.20 260.00 1,274,312.39 2.00 6.00

0.0500 4,901.20 35.00 171,542.05 2.00 20.00

Page 11: Tabla de Datos Para Ms Project

2.00 2.00

2.00 2.00

2.00 2.00

14,703.60 1,448,452.08 TOTAL (10)

0.0500 230.05 24.27 5,583.28 2.00 20.00

230.05 5,583.28 TOTAL (10)0.00 0.00 1.00 1.00

0.00 0.00 1.00 1.00

1.00 5.000.00 0.00 TOTAL (10)

0.0500 1,326.23 0.37 490.70 1.00 1.00

1.00 5.00

1.00 1.00

1.00 1.00

1.00 0.50

1,326.23 490.70 TOTAL (10)

0.0550 1,458.85 2.07 3,019.82 3.00 3.00

0.1250 3,315.57 42.00 139,253.99 3.00 18.00

3.00 3.00

3.00 3.00

3.00 0.60

4,774.42 142,273.81 TOTAL (10)

0.0500 1,326.23 8.13 10,782.24 7.00 28.00

0.0550 1,458.85 3.00 4,376.55 7.00 14.00

0.1050 2,785.08 280.00 779,822.36 7.00 28.00

0.0550 1,458.85 19.50 28,447.60 7.00 0.000.2500 6,631.14 3.00 19,893.43 7.00 0.00

13,660.15 843,322.18 TOTAL (10)

0.0500 223.71 9.30 2,080.47 10.00 20.00

Page 12: Tabla de Datos Para Ms Project

0.1500 671.12 80.00 53,689.44 10.00 20.00

0.0300 134.22 25.00 3,355.59 0.001,029.05 59,125.50 TOTAL (10)

1.0000 49.76 515.00 25,626.40 0.00

49.76 25,626.40 TOTAL (10)

1.0000 60.00 455.00 27,300.00 0.00

60.00 27,300.00 TOTAL (10)

Page 13: Tabla de Datos Para Ms Project

TRABAJO PLANIFICADO

8.00 0.00

8.00 0.00

TOTAL (10) 0.00 #DIV/0!8.00 0.008.00 0.008.00 0.008.00 0.008.00 0.008.00 0.00

TOTAL (10) 0.00 #DIV/0!

8.00 0.00

TOTAL (10) 0.00 #DIV/0!

8.00 48.00

8.00 144.00

8.00 96.00

8.00 48.00

8.00 48.00

TOTAL (10) 384.00 117.77

8.00 48.00

8.00 16.00

TOTAL (10) 64.00 35.388.00 24.00

8.00 24.00

8.00 120.00TOTAL (10) 168.00 70.35

JORNAL DIA (9)

TRABAJO DIA (10)=(8)X(9)

DURACION (11)=(4)/(10)

Page 14: Tabla de Datos Para Ms Project

8.00 24.00

8.00 120.00

8.00 24.00

8.00 24.00

8.00 12.00

TOTAL (10) 204.00 27.24

8.00 24.00

8.00 120.00

8.00 24.00

8.00 24.00

8.00 12.00

TOTAL (10) 204.00 40.84

8.00 24.00

8.00 120.00

8.00 24.00

8.00 24.00

8.00 12.00

TOTAL (10) 204.00 40.84

8.00 8.00

8.00 24.00

8.00 8.00

8.00 8.00

8.00 8.00

TOTAL (10) 56.00 19.60

8.00 16.00

8.00 48.00

8.00 160.00

Page 15: Tabla de Datos Para Ms Project

8.00 16.00

8.00 16.00

8.00 16.00

TOTAL (10) 272.00 24.51

8.00 160.00

TOTAL (10) 160.00 76.688.00 8.00

8.00 8.00

8.00 40.00TOTAL (10) 56.00 12.93

8.00 8.00

8.00 40.00

8.00 8.00

8.00 8.00

8.00 4.00

TOTAL (10) 68.00 22.12

8.00 24.00

8.00 144.00

8.00 24.00

8.00 24.00

8.00 4.80

TOTAL (10) 220.80 35.37

8.00 224.00

8.00 112.00

8.00 224.00

8.00 0.008.00 0.00

TOTAL (10) 560.00 37.89

8.00 160.00

Page 16: Tabla de Datos Para Ms Project

8.00 160.00

8.00 0.00TOTAL (10) 320.00 12.78

8.00 0.00

TOTAL (10) 0.00 #DIV/0!

8.00 0.00

TOTAL (10) 0.00 #DIV/0!